SERVICES
& PROCESS
What to expect when you work with us.
Architectural projects and approvals involce many stages and have complicated procedures. Here is our guide to show you how to it is organized, along with benchmarks, timelines, and anticpated costs.
We look forward to working with you!
Schematic design & preliminary pricing
Timeline: Up to 2 – 3 months, typically
Meetings: One to four, typically
Tasks:
- Site visit to measure building/ documentation of field conditions and input into CAD format
- Create schematic level floor plans, hand-sketched perspectives, with discussion on finishes
- Explore different design directions and select one
- Preliminary pricing / Rough Order of Magnitude (ROM) from Owner’s general contractor (if desired) and design approval by client before proceeding to next phase
Design development & construction documents
Meetings: One to four, typically
Tasks:
- Develop site plan, floor plans, reflected ceiling plans including electrical andlighting, elevations (interior and exterior), sections (if required), and outline specifications (if required)
- Finalize site plan, floor plans, reflected ceiling plans including electrical andlighting, elevations (interior and exterior), sections (if required), architectural details, door/window/ finish schedules, and final outline or full specifications of materials and products (if required)
- Hire consultants and coordinate services and consultant drawings
- Building Permit Application for site permit if required (Partial Design Development).
- Variance submittal if required (Partial Design Development)
Permitting & final pricing
Meetings: One, typically
Purpose: Obtain City or County approval for construction
Tasks:
- Building Permit Application or addendum. Respond to various City / County Agency requests for information/ code interpretations. Assist with obtaining final pricing on project, and/or prepare bid documents to obtain bids
- Answer questions from the Contractor(s), assist with selection and preparation of the Construction Contract
Required:
• Consultant(s) Documents (Structural engineer, lighting, mechanical/ electrical if required)
• Title 24 Energy Report
Notation about permitting:
We have completed 900+ projects throughout the Bay Area, with each jurisdiction having a unique planning process. Because we’re familiar with the relevant codes, we’re able to design projects that get approved!
Construction Administration
Timeline: Depends on construction schedule and contractor. Usually, several hours per week for questions, bi-weekly site visits, etc.
Meetings: As required
Purpose: Administration of construction contract, Client representation
Tasks:
- Site visits as required, construction observation
- Answer questions from contractor
- Site visits as required, construction observation
- Review payment requests
Completion
Timeline: As required
Meetings: As required
Purpose: Close out project
Tasks:
- Issuance of Certificate of Final Completion
- Punch list
- Completion of construction